Ground Gas Membrane Installation

This commercial unit being built on a brownfield site had a requirement for ground gas measures to Characteristic Situation rating 2 (as per BS8485:2015+A1 :2019). Our member assisted the main contractor with the design and installed Juta GP1 ground gas membrane with their NVQ2 qualified technicians. On completion the membrane was independently verified by a verification company (in accordance with Ciria C735) and a report submitted to the local authority which enabled the planning condition to be discharged.

These measures will protect the occupants of this building (when it’s completed) for decades to come.